Good Intention List August 2011, as at 1 Aug 11 |
|
|
|
|
A |
Complete Steering Gear Reinstatement |
SURVEY ITEM |
|
|
|
1 |
Fit new rudder box tops |
Jack's Team |
2 |
Repair quadrant |
Onshore Engineers |
3 |
Refit quadrant |
All |
4 |
Paint steering chains & get chain wheels working |
Jack's Team |
5 |
Test for smooth operation when steam up |
Jack |
|
|
|
B |
Annual Boiler Survey |
SURVEY ITEM |
|
|
|
1 |
Reassemble boilers |
John A's Team |
2 |
Hot Survey boilers |
Surveyor |
3 |
Do settings & test |
John A's Team |
|
|
|
C |
Gear Room |
|
|
|
|
1 |
Complete painting at present scaffold level |
Kevin |
2 |
Descale inside crane from roof |
Richard's Team |
3 |
Place supports for Ardex |
Richard's Team |
4 |
Seal in & around columns with Ardex |
Ardex Placer |
5 |
Refurbish aft angled cladding over lift cables |
Stu's Team |
6 |
Raise scaffolding - last week August? |
Workzone |
7 |
Fit new stanchions & rails on to sides of roof |
Stu's Team |
8 |
Fit reconditioned brake guides |
Stu's Team |
9 |
Fit new Brake Cover |
Stu's Team |
10 |
Complete Stbd big wheel derusting & painting |
Richard, Kevin |
11 |
Repaint all cladding |
Volunteers |
12 |
Paint roof |
Volunteers |
13 |
Fit new switch board, wiring & lights to crane |
Mike |
14 |
Reinstate electricity to Gear Room |
Mike |
15 |
Finesse Gear Room interior |
Jim's Team |
16 |
Reinstate side weight trolleys |
All |
|
|
|
D |
Cathedral |
|
|
|
|
1 |
Remove scrap wires - after boiler survey 27/8? |
John F's Team |
2 |
Stack remaining wires on new racks |
John F's Team |
3 |
Refit any loose decking - for safety |
John F's Team |
4 |
Paint deck heads - RIPO, Green, top coat |
John F's Team |
5 |
Tidy up all remaining items |
John F's Team |
6 |
Vacuum out any material from bilges |
John F's Team |
|
|
|
Other |
|
|
|
|
1 |
Fit additional chocks to support hull |
Chippie Bros |
2 |
Investigate Wheelhouse leak |
Chippie Bros |
3 |
Make tender cover |
Jaz/Louise |
4 |
Complete fitting new decking for bilge pump |
Kerry |
5 |
Clean and paint bilge pump area and decking |
Kevin/Chris |
6 |
Repair & improve electrics |
Bill/Mike |
7 |
Gas axe out opening in port for'd davit |
Neil |
8 |
Make new cover plates for davit holder openings |
Neil |
9 |
Repair crane ladder - on deck |
Neil |
10 |
Make good stbd aft deck, framing & gratings |
Jack's Team |
11 |
Plan Gangway refurbishment |
Malcolm |
12 |
Plan timber deck refurbishment |
Bruce/Malcolm |
13 |
Reinstate fuel heater lines |
Hardistys |
14 |
Test waste oil |
John A |
15 |
Fit new silver insulation wrap over hot pipes |
Diana's Team |
16 |
Set up emergency cement buckets |
Malcolm |
17 |
Set up bilge leak alerts |
Malcolm |
18 |
Paint two pot Crabapple on deck touch ups |
Volunteer |
19 |
Descale & paint capstans |
Volunteer |
20 |
Descale & paint stbd davits |
Volunteer |
21 |
Continue coatings black deck gear |
Chris/Brent |
22 |
Clean up and paint for'd winch |
Brent |
23 |
Repaint white deck houses |
Brent & All |
24 |
Paint short pipe in stbd capstan steam line |
Chris |
|
|
|
Outlook 2011 |
|
|
|
|
1 |
Annual Boiler Survey - Survey Item |
August |
2 |
Finish Cathedral Void Space |
Sept |
3 |
Finish Steering Gear Reinstatement - Survey Item |
Aug - Sept |
4 |
Finish Gear Room |
Aug - Sept |
5 |
Get ready for sea trials |
Sept - Nov |